Opera di rete Castelpagano – Morcone

This is a major strategic project that Renexia S.p.A. will carry out for Terna, connecting the SE Castelpagano (existing) to the future SE Morcone with a 150kV overhead line, and another Terna single line, also equipped with 150kV, to connect the SE Morcone to the future Pontelandolfo marshalling yard.

Description: The construction of new wind power plants in the province of Benevento required an expansion of the national electricity grid managed by Terna. In particular, Renexia S.p.A., which is involved in the construction of the Circello and Casalduni wind farms, will build a high-voltage grid for Terna, connecting it with a 150kV overhead line, SE Castelpagano (existing) to the future SE Morcone, and another Terna single line, also equipped with 150kV, to connect SE Morcone to the future Pontelandolfo marshalling yard.

The entire power line is about 23 km long, including the connection to SE Morcone.

The amount of the works is about € 16M.